Hadley v Baxendale (1854) 9 ExCh 341, [1843-60] All ER Rep 461- (Case Commentary)
Introduction
Hadley
v Baxendale (1854) 9 Exch 341, [1843-60] All ER Rep 461 is a
leading English contract law case. It sets the leading rule to determine
consequential damages from a breach of contract: a breaching party is liable
for all losses that the contracting parties should have foreseen but is not
liable for any losses that the breaching party could not have foreseen on the
information available to him.
It
is basically a formative case dealing with the circumstances in which damages
will be available for breach of contract. The decision of Hadley
v Baxendale has been a prominent case in many common law jurisdictions. It has been applied consequently in the
English, US, and Australian jurisdictions.
The
case establishes that the test of remoteness in contract law is contemplation.
Damages are available for loss which:
1. naturally
arises from the breach according to the usual course of things; or
2. is
within the reasonable contemplation of the parties at the time of contracting
as the probable result of a breach (this may be, for example, because special
circumstances have been communicated at the time of contracting and therefore
can be said to be within their reasonable contemplation)
It
was established in this case that the claimants may only recover losses which
reasonably arise naturally from the breach or are within the parties’
contemplation when contracting.
Background
Facts
The
claimants, Mr. Hadley, and another, were millers and meal men and worked
together in a partnership as proprietors of the City Steam-Mills in Gloucester.
They cleaned grain, ground it into meal, and processed it into flour, sharps,
and bran. A crankshaft of a steam engine at the mill had broken and Hadley
arranged to have a new one made by W. Joyce & Co. in Greenwich. Before the
new crankshaft could be made, W. Joyce & Co. required that the broken
crankshaft be sent to them to ensure that the new crankshaft would fit together
properly with the other parts of the steam engine.
Hadley
entered into a contract with the defendants Baxendale and Ors, who were
operating collectively as common carriers under the name Pickford & Co., to
deliver the crankshaft to engineers for fixing by a certain date at a fee of £2
sterling and 4 shillings.
Baxendale
failed to deliver on the date asked by Hadley, causing him to lose his
business. Hadley sued for the estimated profits he had lost due to Baxendale's
late delivery, and the jury granted Hadley damages of £25. Baxendale appealed, arguing
that he did not know that Hadley would bear any damage because of the late
delivery.
The
question raised by the appeal, in this case, was whether a defendant in a
breach of contract case could be held liable for damages that the defendant was
not aware would be incurred from a breach of the contract.
Issues
Whether
a defendant in a breach of contract can be held liable for damages that the
defendant was not aware would be incurred from a breach of the contract.
Procedural
History:
The
trial court awarded Hadley damages of £25 in the form of lost profits.
Baxendale appealed.
Rule
of Law or Legal Principle Applied:
A
non-breaching party to a contract may recover damages that are reasonably
foreseeable to the parties at the time of contract formation. The non-breaching
party is also entitled to recover damages arising from circumstances that were
communicated to all known parties at the time of contract formation.
Held
The
Court found for the defendant, viewing that a party could only successfully
claim for losses stemming from breach of contract where the loss is reasonably
viewed to have resulted naturally from the breach, or where the fact such
losses would result from breach ought reasonably to have been contemplated of
by the parties when the contract was formed. As Baxendale had not reasonably anticipated
the consequences of delay and Hadley had not informed him of the same, he was
not liable for the mill’s lost profits.
A
non-breaching party is entitled to the damages arising naturally from the
breach itself or those that are in the reasonable contemplation of the parties
at the time of contract. In this case, while the breach by Defendants was the
actual cause of the lost profits of the plaintiffs, it cannot be said that
under ordinary circumstances such loss arises naturally from this type of
breach. There is a variety of reasons for a miller to send a crankshaft to a
third party. The defendants had no way of knowing their breach would cause a lengthier
shutdown of the mill, resulting in a considerable loss. Further, the plaintiffs
never conveyed the special circumstances to the defendants, nor did defendants
know of these stipulations.
Analysis
When
the plaintiff and the defendant entered into a contract, Hadley did not inform
Baxendale that any interruption or postponement in shipping would result in
Hadley’s lost profits. Since Baxendale did not know of Hadley’s special
circumstances, that his mill was inoperable until the new shaft was delivered,
the special circumstances were not reasonably foreseeable at the time the contract
was formed.
The
decision of the court of exchequer, that when one party breaches, the other
party may recover damages that are reasonably foreseeable to both parties at
contract formation is reasonable. The non-breaching party may also recover
damages arising out of any special circumstances so long as those circumstances
were communicated to and known by all parties.
Here,
Hadley’s failure to reveal his special circumstances prevented him from
recovering damages. Hadley never enlightened Pickford and Co. that his mill
operation was completely dependent on receiving a new shaft. The court sparks
light on the subject that that not all broken mill shafts render the mill
inoperable causing a loss in profits. For instance, some may have a a temporary
mill shaft for use when the broken one is out for restoration. As a result,
Baxendale is not liable for the damages arising out of Hadley’s unknown
circumstances.
Hadley v. Baxendale established a limitation on damages to those which naturally result from a breach and are reasonably contemplated by the contracting parties at contract formation. These damages are known as consequential damages.
Conclusion
To
conclude, it can be said that, Hadley v. Baxendale was one of the most commemorated
cases in contract law, which sets forth the default rule that unforeseeable
consequential damages are unrecoverable. The case has come to represent an
important limit to the general rule awarding full expectation damages for
breach Hadley takes on great significance in the literature as an archetype for
contract default rules that improve an economic system.
Where
two parties have entered into contract which one of them has breached, the
damages which the other party should receive in respect of such an infringement
should be fairly and practically be considered either arising naturally, i.e.,
according to the usual course of things, from such an infringement itself, or
such as may relatively be supposed to have been in the scrutiny of both
parties, at the time they made the contract, as the probable result of the
breach of it. Now, if the special conditions under which the contract was truly
made were communicated by the plaintiffs to the defendants, and thus were made known
to both parties, the damages consequential from the breach of such a contract,
which they would reasonably anticipate, would be the amount of injury which
would normally follow from a breach of contract under these special
circumstances so known and communicated. However, on the other hand, if these
special circumstances were completely unknown to the party breaching the
contract, he could only be supposed to have had in his contemplation the amount
of injury which would arise usually, and in the great multitude of cases not
affected by any special circumstances, from such an infringement of contract.
-Simran Khurana
Guru Gobind Singh Indraprastha University.
Comments
Post a Comment